Recently, our Guizhou 120,000-ton DMF supporting liquid waste gas incinerator project successfully completed the mechanical completion!

This project plans to build a set of waste liquid and waste gas direct-fired incinerators, including construction drawing design, waste gas feeding system, waste liquid feeding system, combustion assistance and feeding system, incineration system, waste heat recovery system, denitrification system, smoke exhaust system, auxiliary system, electronic control instrument system, etc.
The installation of equipment, pipelines, and bridges is almost finished, and it is now being rectified and single commissioning. Let us look forward to the smooth progress of the next debugging work.